Technical Specifications
Project Overview
Nammu Hydropower Station Project
This 12 MW hydropower generation plant represents a significant achievement in mechanical and electrical engineering, successfully implemented in Vietnam. The project demonstrated exceptional efficiency, moving from initial selection to the first unit's electricity generation in just 11 months. By March 2004, the facility achieved full operational status with all three units contributing to the grid.
Technical Specifications
Total Installed Capacity
Unit Configuration
- 3 Units
- 4 MW per unit
Project Timeline
Key Project Milestones
| Milestone | Date |
|---|---|
| Project Selection | March 2003 |
| First Unit Production | February 2004 |
| Full Plant Commissioning | March 2004 |
Compliance and Standards
- Approval Status
- Vietnamese ApprovalChinese Approval