Technical Specifications
Project Overview
Power Transmission Infrastructure
This large-scale infrastructure project involves the construction of 1776 km of transmission lines and 7 new substations under the Ministry of Water Resources Engineering. This specific segment focuses on the transformation and construction of high-voltage power lines across a 419 km section. The scope includes critical 500 kV transmission lines and 220 kV double loop configurations to support regional power stability.
Technical Specifications
- Total Transmission Line Length
- 419 km
- System Voltage Levels
- 500 kV220 kV
Infrastructure Details
Substation Facilities
Line Specifications Table
| Line Type | Distance |
|---|---|
| 500 kV Transmission Lines | 389 km |
| 220 kV Double Loop | 30 km |