Water Resources Application Project with Bulb Tubular Generators
This project integrates power generation, irrigation, and other lines through comprehensive water resource management. It is equipped with three Bulb Tubular Generating units.



Technical Specifications
Project Overview
Comprehensive Water Resources Application
Located in Tianyang County, Guangxi, this project is a multi-functional water resources application integrating power generation and irrigation capabilities. The infrastructure features a sophisticated navigation and power station system, designed to support both energy production and vessel throughput. It serves as a critical piece of infrastructure for regional navigation and power supply.
Technical Specifications
- Number of Generating Sets
- 3
- Capacity per Unit
- 22 MW
- Generator Type
- Bulb Tubular Generating Sets
Operational Metrics
Annual Throughput Capacity
- Supported Vessel Class
- 1,000 tonners
Project Timeline
Key Milestones
| Date | Event |
|---|---|
| August 2006 | Contract signed for navigation power station and dam monitoring |
| December 18, 2007 | Project opened to navigation; first generating set operation |
| August 2008 | Estimated third set debugging and operation |