The Jinniuping Hydropower Station is a critical infrastructure project designed for the comprehensive utilization of the Gui Jiang River. With a total installed capacity of 60MW, the facility plays a vital role in stabilizing the regional power grid and supporting local economic development. The project features advanced engineering, including the first ship lock construction in the Gui Jiang series, facilitating both energy generation and regional transportation.
Technical Specifications
Turbine Units
- Total Installed Capacity
- 60 MW
- Average Annual Generation
- 241600000 kWh
Construction & Timeline
Key Milestones
| Event | Date |
|---|---|
| Project Start | October 2004 |
| River Closure | September 28, 2006 |
| Station Test Success | December 8, 2006 |
| Formal Installation | January 31, 2007 |
Infrastructure Features