Large-Scale Water Reservoir
This reservoir project serves as a key infrastructure for water management. It provides water storage for irrigation, flood control, and hydroelectric power generation.



Technical Specifications
Overview
Large-Scale Hydraulic Infrastructure
This comprehensive hydraulic engineering project serves as a critical infrastructure asset for flood control, irrigation, and water supply. Designed for long-term reliability, the facility integrates hydroelectric power generation capabilities to support local energy needs. It plays a vital role in protecting downstream farmland and urban areas while enhancing the regional water environment.
Technical Specifications
Dam Dimensions
| Dimension | Measurement |
|---|---|
| Maximum Height | 56.9 m |
| Crest Width | 6 m |
| Total Length | 444 m |
- Dam Construction Type
- Concrete face rockfill dam
Capacity and Performance
Reservoir Performance
- Turbine Configuration
- Two sets of 6300 kW Francis turbine generator units
Project Details
Construction Timeline
- Construction Started: December 2006
- Impoundment: April 2009
- Grid Connection: August 2009
- Primary Applications
- Flood ControlIrrigationWater SupplyHydroelectric Power