5 x 600MW Power Plant Installation
Installation work on a 5 x 600MW power plant. This unit is located in Taishan, Guangdong.



Technical Specifications
Project Overview
Power Plant Installation Overview
This project involved the comprehensive installation of a 600MW power unit. The construction process was completed in 21 months, from the initial steel frame lifting to a successful 168-hour trial operation. The project was delivered with a zero-defect handover and recognized as a model for civilized thermal power construction.
Project Timeline
- Contract Signed
- September 20, 2004
- First Hook Lifting
- March 1, 2005
- Trial Operation Completion
- November 28, 2006
Technical Specifications
Capacity per Unit
Project Milestones
- Construction Duration
- 21 months
- Trial Operation Duration
- 168 hours
Quality & Compliance
Handover Status
- Project Recognition
- Model ProjectNational Thermal Power Civilized Construction